28-May-25 |
by Melinda Lester |
System Entry: Creation of project page.
|
17-Jun-25 |
by Melinda Lester |
System Entry: Project sent for club signatures.
|
17-Jun-25 |
by Melinda Lester |
System Entry: Project signed by Melinda Lester.
|
21-Jun-25 |
by Melinda Lester |
System Entry: Signature Process cancelled by user.
|
21-Jun-25 |
by Melinda Lester |
System Entry: Project sent for club signatures.
|
21-Jun-25 |
by Melinda Lester |
System Entry: Project signed by Melinda Lester.
|
24-Jun-25 |
by Gillian Bradshaw |
System Entry: Project reverted to "Submitted" - Alan Adamo added to the list of signatories.
|
26-Jun-25 |
System Entry |
System Entry: Project signed by Alan Adamo.
|
3-Sep-25 |
by Stacey Giannoulis |
System Entry: Project approved by the District Approval Committee.
|
24-Feb-26 |
by Stacey Giannoulis |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
9-Mar-26 |
by Melinda Lester |
System Entry: Project has been implemented and final report uploaded.
|
27-May-26 |
by Stacey Giannoulis |
System Entry: Final report approved by the District Approval Committee.
|