19-Oct-24 |
by Tom McLarty |
Please provide us the names and emails of two people who will sign this grant application in order to move this to completion.
|
21-Oct-24 |
by Tom McLarty |
System Entry: Project sent for club signatures.
|
22-Oct-24 |
by Tom McLarty |
System Entry: Signature Process cancelled by user.
|
22-Oct-24 |
by Tom McLarty |
System Entry: Project sent for club signatures.
|
22-Oct-24 |
by Dennis Rogers |
System Entry: Project signed by Dennis Rogers.
|
24-Oct-24 |
by Tom McLarty |
System Entry: Project approved by the District Approval Committee.
|
5-Nov-24 |
by Tom McLarty |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
27-May-25 |
by Tom McLarty |
Please complete the final report for this grant as soon as possible. We have allowed extra time due to the time we were able to support these grants.
|
2-Jun-25 |
by Tom McLarty |
It is important to get this final report submitted ASAP. It can affect on the club's eligibility for a grant in 2025-26. Please let us know what we can do to help you get this completed.
|
24-Jun-25 |
by Tom McLarty |
System Entry: Project has been implemented and final report uploaded.
|
29-Jun-25 |
by Tom McLarty |
System Entry: Final report approved by the District Approval Committee.
|