22-Jul-21 |
by Robert Blumberg |
System Entry: Creation of project page.
|
11-Aug-21 |
by Verne Scholl |
System Entry: Project sent for club signatures.
|
11-Aug-21 |
by Verne Scholl |
System Entry: Project signed by Verne Scholl.
|
11-Aug-21 |
by Verne Scholl |
System Entry: Project signed by Verne Scholl.
|
11-Aug-21 |
by Verne Scholl |
System Entry: Project signed by Verne Scholl.
|
13-Aug-21 |
by Sherry Yardley |
System Entry: Signature Process cancelled by user.
|
13-Aug-21 |
by Sherry Yardley |
System Entry: Project sent for club signatures.
|
13-Aug-21 |
by Sherry Yardley |
System Entry: Project signed by Sherry Yardley.
|
17-Aug-21 |
by Verne Scholl |
System Entry: Project signed by Verne Scholl.
|
17-Aug-21 |
by Verne Scholl |
System Entry: Project signed by Verne Scholl.
|
19-Aug-21 |
by Elana Levens-Craig |
System Entry: Project approved by the District Approval Committee.
|
14-Oct-21 |
by James Morrison |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
16-Apr-22 |
by Robert Blumberg |
Work Party to complete House in a Day project is scheduled for April 30, 2022
|
24-May-22 |
by Robert Blumberg |
Work completed April 30, 2022. Photos uploaded. Donation receipt letter and copy of cancelled check uploaded.
|
29-May-22 |
System Entry |
System Entry: Final Report signed by Verne Scholl.
|
30-May-22 |
System Entry |
System Entry: Final Report signed by Sherry Yardley.
|
4-Jun-22 |
System Entry |
System Entry: Final Report signed by Verne Scholl.
|
12-Jun-22 |
by Elana Levens-Craig |
System Entry: Final report approved by the District Approval Committee.
|