6-Jul-20 |
System Entry |
System Entry: Creation of project page.
|
28-Jul-20 |
by Harry Weilage |
System Entry: Project sent for club signatures.
|
28-Jul-20 |
by Harry Weilage |
System Entry: Signature Process cancelled by user.
|
28-Jul-20 |
by Harry Weilage |
System Entry: Project sent for club signatures.
|
28-Jul-20 |
System Entry |
System Entry: Project signed by Harry Weilage.
|
31-Jul-20 |
System Entry |
System Entry: Project signed by Sharon Hanson.
|
3-Aug-20 |
by Bruce A Young |
Request for more information
|
3-Aug-20 |
by Bruce A Young |
System Entry: Signature Process cancelled by user.
|
25-Aug-20 |
by Bruce A Young |
Need Application Completed by Thursday 8/27/2020.
|
25-Aug-20 |
by Bruce A Young |
Need Application Completed by Thursday 8/27/2020.
|
25-Aug-20 |
by Harry Weilage |
System Entry: Project sent for club signatures.
|
25-Aug-20 |
by Harry Weilage |
System Entry: Project signed by Sharon Hanson.
|
25-Aug-20 |
System Entry |
System Entry: Project signed by Harry Weilage.
|
27-Aug-20 |
by Bruce A Young |
Need Signed MOU for club to be eligible for grant. Please take care of this ASAP!
|
6-Oct-20 |
by Bruce A Young |
System Entry: Project approved by the District Approval Committee.
|
20-Oct-20 |
by Steve Sikorski |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
4-May-21 |
by Sharon Hanson |
Following payment, purchase of the display racks were completed. The coverage of the project and purchase by Sunrise Rotary was covered in the local newspaper. The Veterans Memorial was officially opened in October of 2020.
|
6-Dec-21 |
by Sharon Hanson |
This project was completed following the grant award.
|
4-Feb-22 |
by Sharon Hanson |
Please see attached documentation of invoice paid for this project
|
2-Sep-22 |
by Sharon Hanson |
System Entry: Final Report signed by Sharon Hanson.
|
2-Sep-22 |
System Entry |
System Entry: Final Report signed by Harry Weilage.
|
2-Sep-22 |
by Don Norton |
System Entry: Final report approved by the District Approval Committee.
|