19-May-20 |
by Michelle Balog |
System Entry: Creation of project page.
|
19-May-20 |
by Rachel Ossyra |
System Entry: Project sent for club signatures.
|
20-May-20 |
by Michelle Balog |
System Entry: Project signed by Michelle Balog.
|
21-May-20 |
by Rachel Ossyra |
System Entry: Project approved by the District Approval Committee.
|
12-Aug-20 |
by Ed Graziano |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
21-Jan-21 |
by Susan W Linn |
Michelle,
I want to remind you that your club’s District Grant final report is 60 days past due. Final reports are due 30 days after project completion. Please log into your account on matchinggrants.org to complete and upload your final report.
Thanks
|
27-Apr-21 |
by Susan W Linn |
Hi Michelle,
I want to remind you that your club’s final report for P-3321 is due in 5 weeks on Sunday, May 30. If your project is completed, please file you report as soon as possible.
If you have not been able to complete your project due to COVID, let me know right away. Unused funds will not carry over into FY22.
Please let me know if you have any questions.
Thanks
|
13-May-21 |
by Rachel Ossyra |
5-13-21 The Rotary Foundation has approved modifying this project to support the YMCA's after-school care and e-learning and other supportive programs, as the Dictionaries project cannot be implemented at this time due to COVID-19.
|
28-May-21 |
by Michelle Balog |
System Entry: Project has been implemented and final report uploaded.
|
9-Jun-21 |
by Susan W Linn |
System Entry: Project reverted to "Paid".
|
12-Jun-21 |
by Susan W Linn |
System Entry: Project has been implemented and final report uploaded.
|
16-Jun-21 |
by Bill Lyman - Stewardship |
Stewardship review is complete. Meets all necessary criteria. Final report reviewed. Project okay to be approved by District Approval Committee. WL/LG
|
16-Jun-21 |
by Rachel Ossyra |
System Entry: Final report approved by the District Approval Committee.
|