G-1417

Karen C Primary & Secondary Sc

Description

Financing

Documents

Photos

History Logs

Project Description

Region: Africa

Country: Kenya

Location: Karen

Total Budget: $46,327

Area of Focus: Water and sanitation




View Online
Proposal Form

Supply of Clean Water to the Primary School- 1,140 students and 28 teachers , Secondary School 570 students and 20 teachers and the Community around the School with 3,000 people. The Time line is October to December 2017.The Project Funds are required to Drill a new borehole for the two schools and the community and install wash stations, the existing borehole cannot be rehabilitated. The Club members will provide over sight management of the project, source for funds and report on the progress.

Primary Host Partner

District: 9212

Rotary Club of: Karen-Nairobi

Primary Contact: Protus Lumiti

Email: protus@nyumbani.org

Primary International Partner

We are looking for a Club partner. Click here to pledge support for this project. Recording a pledge will make you the Primary International Partner for this project.

Project Status

Need $25,885
This project needs to receive some pledges to go to the next level. Please check the "Financing" tab to see the list of current pledges. Once the amount pledged is equal to the project budget, the status of the project will be automatically changed to "Fully Pledged".
Click here to pledge support for this project.

Project listed for the 2018-19 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

Karen-Nairobi (9212)

18-Sep-17

$1,000

$3,000

$4,000

Remaining Amount to Raise

Additional Club Contribution (Needed) - Add a contribution

$25,885

-

$25,885

Amount Requested from The Rotary Foundation

$13,442

$3,000

$16,442

Total

$46,327

Note: as of July 1, 2015 there is a 5% additional support fee for cash contributions. This fee does not appear in the financials above because it does not apply if the funds are sent directly to the project account (without going through TRF, and therefore without Paul Harris credit). Clubs sending their cash contribution to TRF must be aware they will have to send an additional 5%.

Project Supporting Documents


[18-Sep-17]
Drilling quotation


[18-Sep-17]
Drilling quotation 1


[18-Sep-17]
Wash assessment report

 

Project Photos


There are no photos yet for this project.
Go to the administration page to upload photos.

History Log Entries

18-Sep-17

by Protus Lumiti

System Entry: Creation of project page.