22-Feb-21 |
by Rachel Ossyra |
System Entry: Creation of project page.
|
22-Feb-21 |
by Rachel Ossyra |
System Entry: Project sent for club signatures.
|
22-Feb-21 |
by Rachel Ossyra |
System Entry: Project signed by Rachel Ossyra.
|
22-Feb-21 |
by Rachel Ossyra |
System Entry: Project approved by the District Approval Committee.
|
22-Feb-21 |
by Rachel Ossyra |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
22-Feb-21 |
by Rachel Ossyra |
System Entry: Project has been implemented and final report uploaded.
|
17-Mar-21 |
by Bill Lyman - Stewardship |
Stewardship review is complete. Project spent $497.07 of $500 but otherwise meets all necessary criteria. Final report reviewed. Project okay to be approved by District Approval Committee. WL/LG
|
17-Mar-21 |
by Rachel Ossyra |
System Entry: Final report approved by the District Approval Committee.
|