14-Oct-19 |
System Entry |
System Entry: Creation of project page.
|
16-Oct-19 |
by Randall J Looper |
Bridget,
You put costs in the description but still need to upload a detail budget of income and expenses.
|
18-Oct-19 |
by Randall J Looper |
Bridget,
Please start the signature process on the descriptiom page for both of your grants.
|
18-Oct-19 |
by Bridget Stewart |
System Entry: Project sent for club signatures.
|
18-Oct-19 |
by Bridget Stewart |
System Entry: Project signed by Bridget Stewart.
|
21-Oct-19 |
System Entry |
System Entry: Project signed by Adriene Holcomb.
|
25-Oct-19 |
by Randall J Looper |
System Entry: Project approved by the District Approval Committee.
|
27-Oct-19 |
by Bill Kehl |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
14-Feb-20 |
by Bridget Stewart |
System Entry: Project has been implemented and final report uploaded.
|
15-Feb-20 |
by Randall J Looper |
Bridgit,
Please upload receipts or copies of club checks to the documents section. Also download a copy of the final report from the District website, complete it, sign it and upload it to the documents area.
|
15-Feb-20 |
by Randall J Looper |
Bridgit,
Sorry I didn't see the final report. You are all good.
|
15-Feb-20 |
by Randall J Looper |
System Entry: Final report approved by the District Approval Committee.
|