14-Aug-19 |
by Taylor Eskew |
System Entry: Creation of project page.
|
20-Nov-19 |
by Taylor Eskew |
System Entry: Project sent for club signatures.
|
20-Nov-19 |
by Taylor Eskew |
System Entry: Project signed by Taylor Eskew.
|
13-Jan-20 |
System Entry |
System Entry: Project signed by Thomas Law.
|
24-Apr-20 |
by Taylor Eskew |
System Entry: Signature Process cancelled by user.
|
24-Apr-20 |
by Taylor Eskew |
System Entry: Project sent for club signatures.
|
24-Apr-20 |
by Taylor Eskew |
System Entry: Project signed by Taylor Eskew.
|
24-Apr-20 |
by Taylor Eskew |
System Entry: Signature Process cancelled by user.
|
24-Apr-20 |
by Taylor Eskew |
System Entry: Project sent for club signatures.
|
24-Apr-20 |
by Taylor Eskew |
System Entry: Project signed by Taylor Eskew.
|
14-May-20 |
by Taylor Eskew |
System Entry: Signature Process cancelled by user.
|
14-May-20 |
by Taylor Eskew |
System Entry: Project sent for club signatures.
|
14-May-20 |
by Taylor Eskew |
System Entry: Project signed by Taylor Eskew.
|
14-May-20 |
by Taylor Eskew |
System Entry: Signature Process cancelled by user.
|
3-Aug-20 |
by David Schribman |
The proposal was not sent during the last Rotary year but all project partners are still committed to doing this project this year.
|
31-Aug-20 |
by David Schribman |
carry over grant to 2020-2021.
|
16-Nov-20 |
by Taylor Eskew |
Project completed, reviewed and paid
|
17-Nov-20 |
by Mahbub Ahmad |
System Entry: Project sent for club signatures.
|
17-Nov-20 |
by Taylor Eskew |
System Entry: Project signed by Taylor Eskew.
|
18-Nov-20 |
by David Schribman |
System Entry: Project approved by the District Approval Committee.
|
18-Nov-20 |
by David Schribman |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
18-Nov-20 |
by David Schribman |
System Entry: Project has been implemented and final report uploaded.
|
18-Nov-20 |
by David Schribman |
System Entry: Final report approved by the District Approval Committee.
|