31-May-19 |
by Marianne Barker |
If you’re ready to turn in your application, send it for signatures NOW – on the administration side of the description tab. It must be signed by the primary contact person and the 2019-20 club president by midnight June 1. Before sending, be sure that you’ve addressed questions about your project if we asked any, making the necessary changes. Thank you!
|
31-May-19 |
System Entry |
System Entry: Creation of project page.
|
31-May-19 |
by Jake Hansen |
System Entry: Project sent for club signatures.
|
31-May-19 |
System Entry |
System Entry: Project signed by Jake Hansen.
|
31-May-19 |
System Entry |
System Entry: Project signed by Scott Hansen.
|
15-Jul-19 |
by Ines Crespo |
System Entry: Project approved by the District Approval Committee.
|
25-Jul-19 |
by T. J. Adams |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
15-Mar-20 |
by Marianne Barker |
This is a reminder that you have a report due May 15, 2020 on this project. If not your final report, then write & send a brief history log indicating the % completion of the project and the estimated end date. Late reports on open grants can affect your eligibility for a 2020-21 grant.
|
15-Apr-20 |
by Jake Hansen |
We need to change our project so now we want to donate $500 to Bingham Memorial Hospital to purchase masks to help during the COVID19 pandemic. They have let us know they have a need for the funds to purchase more masks.
|
15-Apr-20 |
by Ines Crespo |
You are approved to change the scope of your project to a covid-19 response. If you aren't purchasing the masks yourselves, be sure to get a receipt or letter from the hospital showing proof of what the grant funds were used for.
|
5-May-20 |
by Jake Hansen |
The grant is now complete. We paid the $500 to Bingham Memorial Hospital and they used the funds to purchase masks. I have uploaded the letter from the hospital into the documents section. Please let me know if we need to do anything else. Thank you!
|
6-May-20 |
by Jake Hansen |
System Entry: Project has been implemented and final report uploaded.
|
7-May-20 |
by Bob Rose |
I have audited this project and I approve it.
|
7-May-20 |
by Ines Crespo |
System Entry: Final report approved by the District Approval Committee.
|