Project Description

Country: USA

Location: Matanuska-Susitna Borough

Total Budget: $4,333

Areas of Focus: Water, sanitation and hygiene, Maternal and child health, Community economic development

Activity Type: Health: General

Summary: Prep land, construct simple pavilion and erect Kids Don't Float Kiosk on a parcel of land in the city of of Houston, Ak.


Little Susitna Park

Installation of "Kids Don't Float" life jacket loaner board, along with "Josh the Baby Otter" water safety material on the parcel of land owned by the City of Houston, Ak. This is the same parcel of land that our club historically uses to end our annual "Little Su Classic" river clean up event and get out of our kayaks and canoes. Due to the nature of the riverbank in this area, we have encountered numerous capsizes, endangering volunteers. This project will create a family friendly place to safely launch canoes, kayaks, and rafts. This project will not allow vehicle access, and will not be suitable for powered boat traffic. The project will be accomplished during the next 3 years, phase one is to prep the land, build a simple 20ft x 20ft open air pavilion of pressure treated common lumber to protect the water safety interpretive material erect and erect the Kids Don't Float kiosk.

The scope of the work for this season:

Cut down trees in area between parking lot and Parks Highway

Pull stumps and level ground, compact gravel

Build forms and pour concrete

Construct pavilion

This area would give a safe, family friend place for gathering, with life jackets available. The whole Mat Su Valley would benefit, and the work would be done by Susitna Rotary Rotarians. Work will be completed by by June 1 2020.

$ 500 Equipment rental to pull stumps and compact ground

$ 741 4" x 6" 10ft treated (24 @ $30.87/ea) A, B, C, D

$ 703 2" x 10" 16ft treated (22 @ $31.98/ea) E

$ 850 1/2" marine plywood (17 @ $49.98/ea) F

$ 192 2" x 10" 12ft treated (8 @ $23.98/ea) G

$ 947 steel roof panels (16 @ $59.16/ea) H

$ 400 10" timberlok screws, galv nails, roofing screws, ridge cap, etc

$4333 subtotal pavilion


Addendum to Project Description (added after the project was signed)

Under Active Rotarian Involvement, please strike the 'a CD with songs' as we do not plan to include CDs in the future.

Project Contact Person

District: 5010

Rotary Club of: Susitna

Primary Contact: Lanissa Grogan

Email: thegrogans@me.com

Project Status

Completed
This project is "Completed". This means the project has been implemented and the report was accepted by the district leadership. The project will stay listed on this website as a testimony of the achievements of the project partners.

Project listed for the 2019-20 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

Susitna (5010)

19-Apr-19

$2,167

$2,166

$4,333

Total

$2,167

$2,166

$4,333

Project Supporting Documents


[23-Jun-20]
Final Report


[2-Mar-20]
HDL Client agreement


[5-Mar-20]
HDL Paid Invoice


[9-Apr-20]
Mat Su Conservation Invoice


[1-May-20]
Matsu permit


[22-Apr-20]
photo print


[23-Jun-20]
rotary subway receipt

 

Project Photos

History Log Entries

19-Apr-19

System Entry

System Entry: Creation of project page.

19-Apr-19

by Vivian Finlay

System Entry: Project sent for club signatures.

19-Apr-19

by Lanissa Grogan

System Entry: Project signed by Lanissa Grogan.

19-Apr-19

by Dan Phillips

System Entry: Project signed by Dan Phillips.

23-Apr-19

by Vivian Finlay

System Entry: Signature Process cancelled by user.

24-Apr-19

by Kathy Timm

System Entry: Project reverted to "Published".

24-Apr-19

by Kathy Timm

System Entry: Project is now "Fully Pledged".

24-Apr-19

by Kathy Timm

System Entry: Project sent for club signatures.

24-Apr-19

by Lanissa Grogan

System Entry: Project signed by Lanissa Grogan.

24-Apr-19

by Dan Phillips

System Entry: Project signed by Dan Phillips.

24-Apr-19

by Alex Slivka

System Entry: Project approved by the District Approval Committee.

25-Aug-19

by Debra Mason

System Entry: Check for DDF payment issued by Foundation Treasurer.

5-Mar-20

by Kathy Timm

Project is ongoing, some documents added

23-Jun-20

by Lanissa Grogan

System Entry: Final Report signed by Lanissa Grogan.

23-Jun-20

System Entry

System Entry: Final Report signed by Dan Phillips.

23-Jun-20

by Brad J. Gamble

System Entry: Final report approved by the District Approval Committee.