30-Oct-18 |
by Brenda McGinnis |
System Entry: Creation of project page.
|
30-Oct-18 |
by Brenda McGinnis |
System Entry: Project sent for club signatures.
|
30-Oct-18 |
by Brenda McGinnis |
System Entry: Project signed by Brenda McGinnis.
|
31-Oct-18 |
by Kathleen Carollo |
System Entry: Project signed by Kathleen Carollo.
|
30-Nov-18 |
by Randall Looper |
System Entry: Project approved by the District Approval Committee.
|
4-Dec-18 |
by Bill Kehl |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
22-Apr-19 |
by Randall Looper |
Brenda,
Please provide a quarterly update on this project.
|
23-Apr-19 |
by Brenda McGinnis |
Work will begin on this project as soon as spring weather at our high elevation allows. Outdoor temperatures will need to moderate for the concrete work. Interact students and their partner, the City of Kemmerer, are ready to implement the project over the next couple of months as outdoor conditions improve.
|
25-Jul-19 |
by Randall Looper |
Brenda,
Can you please complete an update on this project.
|
26-Jul-19 |
by Brenda McGinnis |
Projected completion date for this project is end of July, 2019. A final report will be submitted in August.
|
16-Oct-19 |
by Randall Looper |
Brenda,
Is this project complete? If it is please complete the final report and upload the receipts. If it isn't please do a history log update.
Thanks
Randy
|
29-Jan-20 |
by Randall Looper |
Brenda,
Please enter a quarterly update on the status of this project in the the history log. If it is complete please upload the receipts and final report.
|
9-Apr-20 |
by Randall Looper |
Brenda,
Please enter a quarterly update on the status of this project in the the history log.
|
12-Oct-20 |
by Randall Looper |
Brenda,
You need to enter a quarterly update on the status of this project in the history log section of this grant. It appears this grant is complete. If it is please complete a final report and upload it along with the receipts to the documents area.
|
21-Oct-20 |
by Randall Looper |
System Entry: Project has been implemented and final report uploaded.
|
21-Oct-20 |
by Randall Looper |
System Entry: Final report approved by the District Approval Committee.
|