2-Sep-18 |
by Rachel Ossyra |
System Entry: Creation of project page.
|
16-Oct-18 |
by Rachel Ossyra |
System Entry: Project sent for club signatures.
|
8-Nov-18 |
System Entry |
System Entry: Project signed by Aaron Dunnill.
|
9-Nov-18 |
by Rachel Ossyra |
System Entry: Project approved by the District Approval Committee.
|
30-Nov-18 |
by David Phelps - District Administrator |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
1-Apr-19 |
by Susan W Linn |
This is a reminder that the final report for your 2018-19 District Grant project is due upon completion of your club’s project. To complete your final report, log into your account on the District Grant Website.
|
19-Apr-19 |
by Rachel Ossyra |
I uploaded the Final Report and Documentation received from Julia Mullikin.
|
19-Apr-19 |
by Rachel Ossyra |
System Entry: Project has been implemented and final report uploaded.
|
22-Jun-19 |
by Rachel Ossyra |
System Entry: Final report approved by the District Approval Committee.
|