Country: USA

Location: Casper WY

Total Budget: $8,400

Area of Focus: Water and sanitation

Activity Type: Water: Sanitation

Summary: Purchase and Install two storm water filtration system Gutter Bins to stem the flow of pollution to the North Platte River


The Rotary Club of Casper is planning for its 100th Anniversary Centennial Celebration on May 1, 2019. For a short-term service project, the Rotary Club of Casper has decided to partner with Frog Creek Partners, LLC to purchase [2] Gutter Bins to help prevent future contamination of the North Platte River. A critical part of this service project is to stem the flow of pollution from Casper's streets to improve the health of the North Platte River.

Frog Creek Partners have developed a patent pending Gutter Bin™ storm water filtration system. This system is a catch basin filter insert that can help solve the pollution problems in the North Platte River. The Gutter Bin captures many kinds of municipal pollution including trash, sediment, and hydrocarbons. It is a cost-effective device that maximizes regulatory compliance and minimizes operating costs by preventing clogged storm sewer lines. The Gutter Bins are accompanied with a Clean and Measure Pollution Service (CAMPS). CAMPS is an ongoing maintenance program where each Gutter Bin™ is cleaned and measured monthly or upon determined schedule. The empirical aspect of the Gutter Bin will help the City of Casper with future regulatory mandates within their MS4 (Municipal Separate Storm Sewer System) permit because of the ability to quantify the amount of pollution capture per bin. Besides the regulatory drive for clean water, we believe this program aligns with Rotary's clean water and sanitation area of focus.

We believe that this is just the beginning of this project as more partners sign on to purchase more Gutter Bins. In addition, clean water is not only important here in Casper but in the world. As we are successful in reducing the pollutants that seep into the North Platte River by our storm water system, this technology can then be used in other parts of the country and the world.

Therefore, Rotary Club of Casper seeks to purchase [2] Gutter Bin™ storm water filtration systems and one year of the Clean and Measure Pollution (CAMP) Service to maintain each bin, for an initial investment of $8400.00. Frog Creek Partners, LLC will work closely with the Rotary Club of Casper and the City of Casper to determine the best location to install the bins.

Project Contact Person

District: 5440

Rotary Club of: Casper

Primary Contact: Barry Johnson

Email: bjohnson7752@gmail.com

Project Status

Reported
This project is "Reported". This means that a report has been forwarded for review to the district leadership. This report is now being reviewed by the district leadership for approval. Once the report is accepted, the status of the project will be changed to "Completed".

Project listed for the 2018-19 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

Casper (5440)

22-May-18

$4,400

$4,000

$8,400

Total

$4,400

$4,000

$8,400

Project Supporting Documents


[22-May-18]
Gutter Bin Budget


[22-May-18]
Gutter Bin Spec Sheet

 

Project Photos

History Log Entries

22-May-18

by Barry Johnson

System Entry: Creation of project page.

23-May-18

by Barry Johnson

System Entry: Project sent for club signatures.

23-May-18

by Barry Johnson

System Entry: Project signed by Barry Johnson.

1-Jun-18

System Entry

System Entry: Project signed by Richard Schwahn.

4-Jun-18

System Entry

System Entry: Project signed by Dick Jay.

8-Jun-18

by Randall Looper

System Entry: Project approved by the District Approval Committee.

9-Jul-18

by Bill Kehl

System Entry: Check for DDF payment issued by Foundation Treasurer.

4-Oct-18

by Randall Looper

Please provide a quarterly update as to the status of this project.

11-Oct-18

by Barry Johnson

The first Gutter Bin has been ordered and the placement of the first Gutter has been determined. The placement will be near David Street Station which gets a fair amount of foot traffic and is near the Rotary Clock. We are waiting for the production of the Gutter Bin and will install the Gutter Bin soon after we receive it from production. The second Gutter Bin will be order sometime in the first quarter 2019.

11-Oct-18

by Randall Looper

System Entry: Project has been implemented and final report uploaded.