P-2139

Bike Trail Drinking Fountain

Description

Financing

Documents

Photos

History Logs

Project Description

Country: USA

Location: Hastings, NE

Total Budget: $1,500

Area of Focus: Economic and community development

Activity Type: Community Development: General

Summary: A drinking fountain to be installed along the Pioneer Spirit Trail for trail users.


The Pioneer Spirit Trail is a 10 mile hike/bike trail that does not have a water station. This heavily used trail will provide water to trail users. The anticipated completion of the drinking fountain would be September 2018.

Project Contact Person

District: 5630

Rotary Club of: Hastings

Primary Contact: Jeff Hassenstab

Email: jhassenstab@cityofhastings.org

Project Status

Paid
This project is "Paid". This means that the funds from the district have been issued. This project is now being ready for implementation. When this is done, a report needs to be uploaded on the project page and the "Reported" button needs to be clicked, then the status of the project will be changed to "Reported".

Project listed for the 2018-19 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

Hastings (5630)

14-May-18

$1,000

$500

$1,500

Total

$1,000

$500

$1,500

Project Supporting Documents


[14-May-18]
990


[14-May-18]
MOU

 

Project Photos


There are no photos yet for this project.
Go to the administration page to upload photos.

History Log Entries

14-May-18

System Entry

System Entry: Creation of project page.

25-May-18

by Vickie Klein

System Entry: Project sent for club signatures.

5-Jun-18

System Entry

System Entry: Project signed by Jeff Hassenstab.

14-Aug-18

by Don Peterson

System Entry: Project approved by the District Approval Committee.

14-Aug-18

by Randy Kratochvil

System Entry: Check for DDF payment issued by Foundation Treasurer.