P-2100

Westmont Elementary School

Description

Financing

Documents

Photos

History Logs

Project Description

Country: USA

Location: Huntington Beach

Total Budget: $4,430

Area of Focus: Basic education and literacy

Activity Type: Education: Literacy

Summary: Purchase of a new kiln which would allow the Westmont Elementary Students to intertwine the arts into their learning.


The Principal and Teachers of Westmont believe that having a kiln to make ceramic projects would benefit all Students. They desire to intertwine the arts into the Students learning and having the kiln would allow Students of all grade levels to learn and explore using clay as a medium. Students will develop their creative side while providing their families with a lasting treasure their Students made just for them. Rotarians will be involved on a rotational cycle where they would set up the kiln and then fire it up with the Student's work. This will be a fun and creative way for kids to interact with our Rotary Members. The kiln will be delivered in the Fall of 2018.

Project Contact Person

District: 5320

Rotary Club of: Huntington Beach

Primary Contact: Richard W Deaner

Email: dick.deaner@yahoo.com

Project Status

Completed
This project is "Completed". This means the project has been implemented and the report was accepted by the district leadership. The project will stay listed on this website as a testimony of the achievements of the project partners.

Project listed for the 2018-19 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

Huntington Beach (5320)

1-May-18

$2,215

$2,215

$4,430

Total

$2,215

$2,215

$4,430

Project Supporting Documents

Project Photos


There are no photos yet for this project.
Go to the administration page to upload photos.

History Log Entries

1-May-18

by Richard W Deaner

System Entry: Creation of project page.

27-May-18

by Richard W Deaner

System Entry: Project sent for club signatures.

27-May-18

by Richard W Deaner

System Entry: Project signed by Dick Deaner.

29-May-18

System Entry

System Entry: Project signed by Nancy Gahn.

5-Jul-18

by Stacey Giannoulis

System Entry: Project approved by the District Approval Committee.

21-Aug-18

by Helen Maxwell

System Entry: Check for DDF payment issued by Foundation Treasurer.

4-Mar-19

by Richard W Deaner

Check Number 1051 for $4,339.82 was written on 10/29/18 and presented to Westmont on 11/1/18.

13-Mar-19

by Richard W Deaner

System Entry: Project has been implemented and final report uploaded.

5-Apr-19

by Stacey Giannoulis

System Entry: Final report approved by the District Approval Committee.